Schedule of the activity
Duration: 4 hours
Sprint timeline
The workshop involves three sprints of three workdays (i.e. 8 minute blocks). Each sprint takes 45 minutes.
- Sprint planning with product owner: 5 minutes (writing task cards, prioritization)
- Day 1 stand-up: 2 minutes (no work allowed, only discussion of who did what and will do what)
- Day 1 work: 8 minutes
- Day 2 stand-up: 2 minutes (no work allowed, only discussion of who did what and will do what)
- Day 2 work: 8 minutes
- Day 3 stand-up: 2 minutes (no work allowed, only discussion of who did what and will do what)
- Day 3 work: 8 minutes
- Demonstration to product owner: 5 minutes (goals for next sprint are communicated)
- Retrospective: 5 minutes (4 minutes in team, 1 minute for finding themes across teams)
Activity timeline
- 00:00 - Introductions, separating in teams
- Name tags “the agile way” (blue painter’s tape and sharpie)
- Assign teams randomly
- Request that each team appoints a scrum master
- Watch agile scrum video
- 00:10 - What is agile?
- Introduction on agile methodology
- Agile manifesto
- Development cycle and recurring milestones
- 00:20 - The mission!
- Presentation on the CubeSat Mission Objectives (see templates)
- 00:40-01:25 - Sprint 1 (see above)
- 01:25-02:10 - Sprint 2 (see above)
- 02:10:02:55 - Sprint 3 (see above)
- 02:55-03:15 - Break
- 03:15 - Chair flying (10 minutes per team)
- mission director acts as ground control and asks questions related to the acceptance criteria,
- team acts out launch (check weight balance) and first orbit (check power status while in Earth’s shadow).
- 03:45 - Close-out discussion and reflection
- Did you experience increased productivity in the later sprints?
- What do you think are the advantages of this way of working in teams?